When a Major Project Needs a Reset, Not Another Explanation
GLOBAL CASE STUDY SERIES No. 2
INFRASTRUCTURE THAT LASTS
Part 4 | Chapter 17
How Governments Rebuild Scope, Cost and Schedule Before a Troubled Project Becomes a Permanent Fiscal Problem
Published: 19 August 2026
Most troubled infrastructure projects do not fail on the day government finally admits there is a problem.
The failure usually began much earlier.
A completion date was kept after the construction sequence had already made it unrealistic. A cost estimate remained in the Cabinet paper even though contractor claims and design changes had overtaken it. Land acquisition fell behind, but procurement continued. The operating agency discovered that the facility would cost more to run than expected. Another funding request arrived and was approved because stopping the project seemed politically harder than continuing it.
By the time senior government becomes involved, the project may already have several versions of reality. Contractors are forecasting from the work in front of them, the project office may be working from revised assumptions, while the finance ministry is still relying on the last formally approved baseline. Once those positions have diverged materially, another progress report will not restore control. Government needs to establish a credible project position again.
Chapter 16 dealt with authority: who can delay, escalate or return a major project for reassessment. This chapter addresses what should happen after that authority is used.
A genuine project reset is not simply a new completion date and a larger budget.
It is a controlled reconstruction of the government's decision.
First Establish Whether the Old Baseline Is Still Real
The first question I would ask a troubled project is surprisingly basic.
Can the existing approved baseline still be achieved?
Do not ask whether the team is “working toward it.” Do not ask whether management remains “committed” to it.
Ask whether the remaining scope can credibly be delivered within the approved cost and schedule.
If the answer is no, continuing to report performance against that baseline can become misleading. A schedule that everybody privately knows cannot be achieved no longer functions as a management tool.
The British government's current reset of High Speed Two is useful precisely because this point became explicit.
By 2025, the previously stated 2029–2033 service range was no longer considered achievable. HS2 Ltd and the Department for Transport then examined the remaining work and produced revised cost and schedule ranges. In May 2026, government published an expected Phase 1 cost range of £87.7–£102.7 billion. The indicated service range for Old Oak Common to Birmingham Curzon Street is May 2036 to October 2039, while the wider route through Euston has a later range. A fully re-baselined programme is being developed around those revised assumptions.
The significance is not the size of HS2.
It is what government did when the old timetable could no longer serve as a credible control.
It stopped pretending that the previous date remained the management target.
That is the first discipline of a reset.
Do Not Start by Asking How Much More Money Is Needed
When a project gets into difficulty, the discussion often moves too quickly to additional funding.
I would resist that.
Before asking how much more money the project needs, establish what government is still trying to build.
Scope on a troubled project is rarely as stable as the original approval paper suggests. Design develops. Requirements are added. Contractors interpret obligations differently. Interfaces multiply. Some facilities may no longer be essential. Others may have become unavoidable because construction has progressed too far to change economically.
HS2's current reset has included a review of remaining scope, commercial arrangements, organisational capability and the relationship between HS2 Ltd, the Department for Transport and wider government. The government has also required the programme business case to be updated to reflect the changed delivery position.
That ordering matters.
If government agrees the new money first, the existing scope tends to survive by default.
A reset should reopen the scope question before the revised cost becomes politically fixed.
Some elements may remain untouched. Others may need simplification, phasing or redesign. A requirement that was reasonable eight years ago may have become poor value after cost escalation or changes in demand.
There is no shame in changing scope when circumstances have changed.
The mistake is changing the budget while pretending the original decision remains intact.
Recalculate the Remaining Job, Not the History
A recovery team inherits an enormous amount of historical information: original contract prices, previous budget approvals, settled claims, expenditure already incurred, earlier schedule assumptions, political commitments and consultant reports. Those records remain important for accountability, but they should not dominate the recovery estimate.
The immediate task is to establish the cost and time required from today forward to complete the remaining approved outcome. That requires a fresh look at unfinished design, remaining quantities, contractor productivity, unresolved claims, interfaces, testing and commissioning, land and utility constraints, regulatory approvals, and the organisation's actual capacity to manage the work that remains.
One difficulty is that governments often become anchored to earlier numbers. A project first approved at $3 billion may now require another $4 billion to complete after $2.5 billion has already been spent, yet officials may continue referring to the original figure because it is politically familiar. The decision before Cabinet, however, concerns what should be done with the project now. Historical expenditure explains how government reached the current position; it does not establish what the remaining work will cost.
Historical expenditure helps explain how the government arrived there. It cannot tell Cabinet what the remaining work will cost.
Crossrail Shows the Cost of Protecting an Unrealistic Date
The Crossrail experience remains one of the clearest warnings.
The project had been working toward a December 2018 opening. The UK's National Audit Office later found that the fixed date drove decision-making even as pressures increased. Multiple activities ran in parallel, the delivery plan was insufficiently detailed, and opportunities to change approach were missed. The NAO identified an absence of an achievable plan among the factors that drove unnecessary cost. Around £2.8 billion of additional financing ultimately had to be provided.
When the programme could no longer maintain the old position, new leadership was brought in and the remaining work was reviewed to establish a deliverable schedule and clearer funding requirement. Crossrail eventually opened as the Elizabeth line in 2022. The Department for Transport subsequently published a dedicated lessons report on the sponsorship experience.
The lesson I would take into a Cabinet meeting is practical.
A politically attractive completion date is not a project control.
If the sequence of remaining work no longer supports it, forcing the project team to keep reporting against that date can encourage increasingly artificial assumptions.
A government loses less credibility by changing an impossible date early than by defending it until the construction site proves it wrong.
A New Baseline Must Not Erase the Old Failure
There is a danger on the opposite side.
Rebaselining can improve control. It can also make poor performance disappear from the dashboard.
If a project is three years late and 40 percent over budget, issuing a new baseline can suddenly make next month's report look green again.
Rebaselining can improve control, but it can also make poor performance disappear from the dashboard. A project that is already three years late and 40 percent over budget may appear healthy again immediately after a new baseline is approved. That is useful for future management only if the historical movement from the original commitment remains visible.
For a government reset, I would preserve both the original approved baseline, including subsequent authorised changes, and the new recovery baseline. Future reporting should show performance against the new baseline while continuing to disclose how far cost, schedule and scope have moved from the position originally approved by government.
This matters because ministers, project directors and administrations will change over the life of a major project. The record should still allow future decision-makers to understand how the project moved from the original commitment to the current one.
Do Not Approve a New Completion Date Until the Remaining-Work Baseline Is Credible
This is one point where I would make the decision rule explicit.
Do not approve a new public completion date simply because the old one has failed.
First establish the remaining sequence of work.
For a transport project, that may mean civil structures, systems installation, power, signalling, rolling stock, testing, safety certification and trial operations. For a water plant, it may involve civil completion, electromechanical equipment, transmission lines, grid connection, commissioning and operator readiness.
The critical path needs to reflect actual dependencies.
Crossrail demonstrated the danger of activities being compressed against a fixed opening date. HS2's current reset has deliberately gone back through the sequence required to finish civil works, stations, rail systems, rolling stock, testing and reliability before passenger operation.
Only then should a new range be taken to the minister.
I prefer a credible schedule range to a false single date when uncertainty remains material.
The same applies to cost.
A government that knows the realistic range of outcomes is in a stronger position than one carrying an artificially precise number that will change again six months later.
Keep Tight Control While the Reset Is Being Built
A project reset can take months.
Construction does not necessarily stop while government rebuilds the baseline.
That creates a dangerous period: the old control framework is no longer credible, but the new one has not yet been approved.
HS2 offers a useful current example. While the full reset and new baseline are being developed, the Department for Transport has used strengthened in-year expenditure controls and an annual performance management plan with construction targets and performance metrics. The department has said those controls will remain until delivery capability improves and the new cost and schedule baseline is established.
I would apply the same principle elsewhere.
Government should identify which spending must continue to protect the asset or maintain productive construction, which commitments require additional approval during the reset, and which scope changes should be frozen until the revised case is decided.
A reset period should not become an administrative vacuum.
Nor should every payment be frozen indiscriminately. That can create claims, demobilisation costs and further delay.
The controls must distinguish between keeping the project productive and allowing new liabilities to accumulate.
Australia Has Already Seen the Same Management Failures Repeatedly
Australia's Department of Finance has published lessons drawn from actual Gateway Reviews across government programs and projects.
They are strikingly practical.
The lessons include appointing dedicated Senior Responsible Officers for complex delivery, defining escalation and decision paths, maintaining decision and scope-change logs, setting risk-escalation thresholds, reviewing critical-path dependencies and expressing risk in terms of time and cost.
Gateway Reviews themselves are short independent reviews conducted at critical points in the lifecycle of high-risk Commonwealth proposals. Their purpose includes early identification of areas requiring corrective action.
For a troubled infrastructure project, I would use that principle during the reset.
Do not ask the same team that defended the old baseline to validate the new one without challenge.
The delivery team knows the project better than anyone. Their knowledge is essential.
Independent assurance is still necessary because the reset is precisely the moment when optimism, institutional reputation and sunk commitments can distort judgment.
The reviewer should test whether quantities are complete, productivity assumptions are credible, risk allowances are realistic, contract positions are understood and the schedule has enough logic behind it to survive independent examination.
A reset signed only by the project team is an internal forecast.
Government needs an assured decision basis.
Productivity Must Be Measured Before It Is Assumed
One of the easiest ways to make a recovery plan look affordable is to assume that future productivity will improve.
One of the easiest ways to make a recovery plan appear affordable is to assume that future productivity will improve. In some cases that assumption is reasonable: new leadership may simplify interfaces, contractors may change working methods, access constraints may disappear, and greater design maturity can materially improve output. The improvement, however, should be demonstrated in project data rather than inserted into the recovery plan as a hopeful percentage.
The HS2 reset is relevant because the government has linked its revised delivery approach to stronger project controls, changed commercial relationships and improved productivity while measuring construction performance during the transition. The appropriate metric will differ by sector. A road project may track earthworks or pavement output per crew-day; a tunnel project may use advance rates; a water network may monitor installed pipe length against labour and access assumptions; and a building project may need trade-package or floor-area productivity measures.
Where the proposed baseline depends on productivity materially above anything the project has previously achieved, that assumption should be shown explicitly in the approval paper, together with the evidence supporting it. Cabinet then sees how much of the recovery case depends on an improvement that has yet to be demonstrated.
If the new baseline depends on productivity that the project has never achieved, Cabinet should see that assumption clearly.
Earned Value Is Useful Only If the Baseline Is Worth Measuring Against
The U.S. Department of Energy uses Earned Value Management to compare actual scope accomplishment, cost and schedule with an approved project baseline. Its active project-management guidance integrates EVM with planning, execution and control for capital projects.
The U.S. Department of Energy uses Earned Value Management to compare actual scope accomplishment, cost and schedule with an approved project baseline. Its project-management guidance integrates EVM with planning, execution and control for capital projects. The method is useful when the underlying baseline remains credible, because it can show whether actual delivery is moving away from the approved plan.
Once the baseline itself has become unrealistic, however, increasingly precise variance calculations do not restore control. Government therefore needs to distinguish between poor performance against a sound baseline and a baseline that no longer represents a deliverable project. The former can usually be addressed through corrective management within the existing approval framework; the latter may require the project to be rebaselined, restructured or returned for a fresh decision.
Without that distinction, a project can remain in “recovery” for years while management continues reporting deviations from assumptions that no longer describe the work that can actually be delivered.
Confusing the two can keep a project in recovery mode for years without ever addressing the assumptions that created the problem.
The Business Case Must Come Back to the Table
Major projects sometimes treat the business case as something completed before procurement.
That is unsafe once a project has moved materially in cost, timing or scope.
HS2's 2026 reset includes an instruction to update the programme business case to reflect changes in delivery.
Major projects sometimes treat the business case as a document completed before procurement, but a substantial change in cost, timing or scope can alter the basis on which the investment was originally approved. HS2's 2026 reset, for example, includes an instruction to update the programme business case to reflect the changed delivery position.
A project justified at one cost and completion date may present a materially different economic case after years of delay or major cost escalation. That decision should also be tested against the wider infrastructure obligations already visible in the five-year portfolio discussed in Chapter 15. Demand may have changed, competing infrastructure may have been completed, technology may offer a different solution, and future operating costs may no longer match the assumptions used at approval.
The reset paper should therefore put a direct question before the approving authority:
If this project were brought to government today, knowing what we now know, would we still approve the remaining investment?
This is not the same as asking whether government has already spent too much money to withdraw. Expenditure already incurred is relevant when comparing the available options, including the cost of cancellation, but it should not by itself justify the next commitment of public funds.
Cancellation Must Be Costed Properly Too
A reset should not assume that cancellation is cheap.
By the time a major infrastructure project reaches serious difficulty, termination may create contractor liabilities, remediation costs, incomplete structures, land obligations, environmental works and years of legal dispute.
In the 2026 HS2 assessment, the Accounting Officer considered a cancellation counterfactual alongside the revised completion case. HS2's chief executive separately advised on cancellation and remediation costs as part of ministerial decision-making.
This is exactly what I would expect.
A reset should not assume that cancellation is cheap. By the time a major infrastructure project reaches serious difficulty, termination may create contractor liabilities, remediation costs, incomplete structures, land obligations, environmental works and years of legal dispute.
In the 2026 HS2 assessment, the Accounting Officer considered a cancellation counterfactual alongside the revised completion case, while HS2's chief executive separately advised on cancellation and remediation costs as part of ministerial decision-making.
That is the level of analysis government needs. Continuing simply because withdrawal is politically difficult can lock in further losses, but cancellation based only on the discomfort of a revised cost estimate may be equally poor judgment. The relevant comparison is between the full cost and consequence of the available options. Depending on the project, those options may include completing the original scope, reducing scope, phasing delivery, pausing selected packages or terminating the project.
A credible reset should place those alternatives before the approving authority before government commits additional public money.
For severely troubled projects, the relevant alternatives may include completing the original scope, reducing scope, phasing delivery, temporarily pausing selected packages or terminating the project.
A credible reset makes those alternatives visible before the government commits itself again.
World Bank Experience Suggests That Restructuring Should Not Be Treated as Failure
Development projects also change during implementation.
World Bank projects can be formally restructured when objectives, scope, components, financing arrangements or implementation conditions need adjustment. Recent World Bank research examining projects over time found that restructuring was associated with sustained improvement in both implementation progress and development-objective ratings compared with similar projects that were not restructured.
Development projects also change during implementation. World Bank projects can be formally restructured when objectives, scope, components, financing arrangements or implementation conditions need adjustment. Recent World Bank research examining projects over time found that restructuring was associated with sustained improvement in both implementation progress and development-objective ratings compared with similar projects that were not restructured.
This does not mean that restructuring will rescue every weak project. It does, however, challenge the bureaucratic tendency to postpone formal change because acknowledging that the original design no longer works may be interpreted as failure. Where the underlying assumptions have materially changed, delaying that recognition can allow additional cost, contractual exposure and implementation problems to accumulate.
Government project systems should therefore make it possible for officials to correct a deteriorating project case while there is still room to change direction. That requires technical evidence, a formal route for approving the change and a political environment in which an early correction is not automatically treated as evidence of poor management
The Reset Team Should Be Smaller Than the Project Organisation
A troubled project often generates additional meetings, committees and reporting layers, although those rarely solve the underlying control problem. The reset itself is better handled by a small team with direct access to the strongest technical, commercial, financial and delivery information available. It should have enough authority to challenge assumptions and obtain evidence quickly, without becoming another permanent management layer.
The distinction in responsibility should remain clear. The existing project organisation continues to deliver the work; the reset team reconstructs the basis on which government will decide how that work should proceed. To do that credibly, it needs direct access to contractor forecasts, quantity data, schedule logic, claims exposure, design maturity, risk registers and funding information.
If significant commercial or technical information is filtered before reaching the reset team, the result is likely to be another management presentation rather than an independent reconstruction of the project's real position.
Its members should be able to obtain contractor forecasts, quantity data, schedule logic, claims exposure, design maturity, risk registers and funding information without waiting weeks for internal clearance.
If the reset team cannot see the real commercial and technical position, it will produce another management presentation.
What I Would Put in the Project Reset Decision Note
For Cabinet, a finance minister or a major-project committee, I would keep the final reset paper short enough that the decision cannot hide inside it.
The supporting analysis may run to hundreds of pages. The Project Reset Decision Note should not.
It should show:
- The decision required now — what government is actually being asked to approve.
- What has changed — cost, schedule, scope, demand, design, contracts or delivery capability since the last approval.
- Remaining work — the scope still required to reach an operational asset, separated from work already completed.
- Credible cost and schedule range — including the principal assumptions and risk allowance behind both.
- Options still available — continue, modify, phase, pause or terminate where those choices remain feasible.
- Interim controls — expenditure, procurement or scope restrictions that remain until the new baseline is stable.
- Residual risks and named owners — especially those capable of forcing another major decision.
- Next return point — the event, threshold or date at which the project must come back to the approving authority.
The original baseline should appear beside the proposed reset position.
Otherwise the decision-maker sees the new future without seeing how far the project has moved.
A Reset Is Finished Only When Government Can Control the Project Again
A project reset is complete only when government has regained enough control to make credible decisions about what happens next. Management should be able to explain what remains to be built, how the remaining sequence works, the realistic cost and schedule range, which risks could still alter that position, who owns those risks and what action will follow if an agreed threshold is crossed. It should also be clear which deviations can be managed within the approved baseline and which would require the project to return for another decision.
If those answers remain uncertain, publishing a revised completion date may improve the appearance of control without restoring it. Crossrail demonstrated the cost of allowing pressure around an opening date to overtake the evidence, while the current HS2 reset shows a government attempting to rebuild the delivery basis while maintaining tighter interim control over expenditure and performance. Australia's Gateway experience adds the value of independent challenge at critical decision points, and U.S. federal practice shows why changes to approved baselines require formal control.
For a government facing a troubled national project, the immediate task is therefore to reconstruct the remaining project before making another public commitment. Once the realistic scope, cost, schedule, risks and available alternatives are visible, the approving authority can decide whether the project still justifies the next commitment of public money — and, if it does, under what conditions government is prepared to proceed.
Sources and Further Reading
UK Department for Transport and HS2 Ltd. HS2 6-Monthly Report to Parliament: May 2026.
UK Department for Transport. High Speed 2 Phase 1: Decision to Continue Delivery Following Programme Reset — Accounting Officer Assessment Summary (2026).
UK National Infrastructure and Service Transformation Authority. NISTA Major Projects Annual Report 2025–26.
UK National Audit Office. Completing Crossrail.
UK Department for Transport and Infrastructure and Projects Authority. Sponsoring a Major Project: The Crossrail Experience (2024).
Australian Government Department of Finance. Gateway Reviews Process (2026).
Australian Government Department of Finance. Lessons Learned — Gateway Reviews (2026).
U.S. Department of Energy. Program and Project Management for the Acquisition of Capital Assets and associated Performance Baseline, Change Control and Earned Value Management guidance.
U.S. Government Accountability Office. Agencies Need to Establish Comprehensive Policies to Address Changes to Projects' Cost, Schedule, and Performance Goals.
World Bank. Why Detours Improve Development Outcomes (2026).
The institutional cases above are used to examine how governments and public institutions regain control of projects after major assumptions have changed. The Project Reset Decision Note is presented here as a practical decision tool for governments considering a significant rebaseline, restructuring or recovery action.
Global Insight 365
Infrastructure, Development Finance and Policy Decisions from the Field
Comments
Post a Comment
Welcome to Global Insight 365.
We value thoughtful discussions and diverse perspectives.
Please share your ideas with respect and kindness.
Together, we build a trusted global knowledge
community.
Global Insight 365에 오신 것을 환영합니다.
우리는 깊이 있는 토론과 다양한 관점을 소중히 생각합니다.
서로를 존중하는 마음으로 여러분의 생각을 나누어 주세요.
함께 신뢰받는 글로벌 지식 공동체를 만들어 갑시다.