Who Has the Authority to Stop a Bad Infrastructure Decision?

 GLOBAL CASE STUDY SERIES No. 2

INFRASTRUCTURE THAT LASTS
Part 4 | Chapter 16

Why Major Projects Need Clear Decision Rights Before Problems Become Commitments

Published: 19 August 2026

The warning signs on a troubled infrastructure project often appear long before the budget crisis.

The engineer sees scope beginning to move. Procurement staff know the market response is weaker than expected. The finance team notices contingency disappearing. Land acquisition is behind schedule, or an operating agency is quietly questioning whether it can afford the facility after completion.

Still, the project moves.

This happens because information and authority are not the same thing.

In public projects I have worked around, one of the most difficult questions is rarely technical. It is administrative and political: Who has the authority to say that the project should not move to the next stage yet?

A committee may contain twenty people and still have no clear answer.

That weakness becomes expensive.

Chapter 15 proposed a five-year view of future infrastructure obligations so that government can see rehabilitation, replacement and new investment pressures together. Visibility is useful only when the institutions receiving that information are able to act on it.

An investment pipeline becomes useful only when government has already defined who may approve, delay, escalate or return a project for reassessment.

A Project Can Have Many Supervisors and Still Have No Owner

Large public projects accumulate committees.

There may be a steering committee, technical committee, procurement committee, project management unit, ministry planning department, finance ministry review team, development partner and consultant.

Their terms of reference can look impressive.

When a serious problem emerges, responsibility frequently becomes less clear.

The project director says the issue requires ministerial approval. The ministry says it relied on the consultant. Finance says the technical assumptions came from the line ministry. The consultant says the decision belonged to government.

By then, months may have passed.

For every major public project, I would require one senior official to be named as the single accountable project owner. That person does not personally manage engineering, procurement or construction. The role exists so that there is one identifiable official responsible for bringing unresolved risks to the appropriate decision level and ensuring that major decisions are recorded.

Several countries use versions of this model.

The United Kingdom uses Senior Responsible Owners for major government projects, while Australia uses Senior Responsible Officers in its assurance system. The terminology is secondary. What matters is that one senior official carries overall accountability while central assurance remains independent of delivery.

That separation needs to remain clear throughout the project. Delivery responsibility should stay with the designated project owner, while independent reviewers test the evidence and raise concerns without taking over management. Decisions that exceed delegated authority should move formally to the minister or Cabinet, with the reasons and remaining risks recorded at that level.

Britain Narrowed the Portfolio So the Centre Could Pay Attention

The United Kingdom offers an interesting current example.

At the end of March 2026, the Government Major Projects Portfolio contained 189 projects with a combined whole-life cost of £924.2 billion. Twenty-nine were rated Green, 109 Amber and 34 Red, while 17 were exempt from a Delivery Confidence Assessment. From 1 April 2026, the government refocused the central portfolio to approximately 80 of its most complex and strategically significant projects.

That change deserves attention.

Central oversight is a scarce resource too.

A finance ministry, cabinet office or central infrastructure authority that tries to supervise every project at the same intensity will eventually supervise none of them properly. High-risk projects require senior attention, specialist challenge and faster escalation. Lower-risk investments should remain primarily within departmental management.

Britain's model keeps delivery accountability with departments while NISTA provides independent scrutiny, assurance and targeted intervention. Its assurance arrangements are increasingly tiered according to risk and complexity, with clearer escalation routes.

For governments designing a similar system, the boundary between delivery and central oversight needs to be explicit. The line ministry should remain accountable for delivering the project, while the central authority concentrates its limited assurance capacity on projects whose scale, complexity or risk justifies additional scrutiny. If the centre begins managing projects on behalf of weak ministries, accountability becomes harder to trace and the assurance function gradually loses its independence. Serious risks should therefore be escalated without transferring routine delivery responsibility away from the sponsoring ministry.

A Red Rating Should Trigger a Decision

Risk dashboards become useful only when each material rating is tied to a predetermined management response. Britain's current system uses a Red Delivery Confidence Assessment to trigger deeper scrutiny and targeted support, with independent ratings used where recent central assurance has taken place. Governments designing their own framework should go further by linking defined thresholds to specific decisions: a major cost increase may require finance-ministry revalidation, a delay extending beyond the approved fiscal period may require Cabinet notification, unresolved land acquisition may prevent tender issuance, and a material change in demand may reopen the economic case. The numerical thresholds will vary by sector and country, but officials should know in advance what action follows when a project crosses them. Otherwise the dashboard records deterioration without changing the decision process.

Korea's PIMAC Shows the Value of an Independent Gatekeeper

Korea provides another model, particularly at the front end of public investment.

KDI's Public and Private Infrastructure Investment Management Center describes its role as a gatekeeper for public investment. Its Preliminary Feasibility Study system examines large proposed government investments before budget commitment, including economic feasibility, policy justification, investment priority, timing and financing. PIMAC also supports reassessment under Korea's Total Project Cost Management system when major projects change in cost, size or implementation conditions.

The institutional lesson is more important than the methodology.

The ministry proposing a project should not be the only institution judging whether that project deserves national funding.

Line ministries know their sectors. They also have incentives to advance their own projects.

An independent fiscal or analytical challenge function gives the government a second view before political commitment becomes difficult to reverse.

This becomes even more important after approval.

A project may have been sensible when originally assessed and still become a poor proposition later. Construction prices change. Demand forecasts weaken. Design scope expands. Land costs rise. Another project may provide the same service more efficiently.

Approval should therefore never create permanent immunity from reassessment.

If a large project changes materially, the evidence should return to the decision table.

Australia Reviews Projects at the Moment the Decision Changes

Australia's Gateway Review process provides a particularly practical model.

For qualifying high-risk proposals, independent teams review projects at critical points in their lifecycle. For infrastructure and procurement proposals, the current Commonwealth threshold includes projects with estimated total costs of A$30 million or more when they are assessed as high risk. Reviews examine matters such as the business need, business case and delivery strategy as projects move forward.

The timing of the review is what gives it practical value. Once contracts are signed, assurance may only explain what went wrong; conducted before a major commitment, it can still influence scope, procurement strategy, funding or even the decision to proceed.

Australia's published lessons from Gateway Reviews are remarkably practical. They call for dedicated senior responsible officers on complex projects, clearly defined escalation and decision-making paths, logs recording decisions and scope changes, risk thresholds for escalation, and senior review of dependencies and critical paths.

These recommendations come from repeated project reviews rather than from an abstract governance model.

One practice is especially worth adopting: every major project should maintain a formal decision log separate from ordinary meeting minutes. For each material change, it should record the decision taken, the evidence considered, the alternatives rejected, the approving authority, the residual risk and the point at which the matter must be reconsidered.

Five years later, a new minister or project director should be able to understand why the government accepted that risk.

Institutional memory should not depend on who still works in the building.

The Minister Should See Disagreement Before It Is Sanitised

There is a common weakness in government briefing.

Technical disagreement disappears on its way upward.

By the time a project paper reaches a minister, genuine professional disagreement is often compressed into neutral phrases such as “manageable risk” or “subject to mitigation.” That can conceal information the decision-maker actually needs. Major submissions should therefore disclose unresolved differences whenever they could materially affect cost, schedule, safety, demand or future operating requirements. If the project team expects land acquisition to take twelve months but the responsible land agency expects thirty, both estimates should appear in the decision paper with the reasons for the difference. The same applies when an operating agency forecasts a recurring subsidy that has not been recognised in the medium-term budget. Senior officials should be asked to resolve the disagreement, rather than receive a document from which the disagreement has already been removed.

New Zealand Puts Senior Sign-Off Behind Portfolio Information

New Zealand Treasury's Quarterly Investment Reporting system provides another useful discipline.

Government agencies update information on investment intentions, upcoming decisions, funding requirements, delivery progress and risks. The information is used to advise the Minister of Finance and support wider investment and Budget management.

The reporting process requires senior organisational sign-off.

That matters because portfolio data often begins deep inside a ministry.

When the agency head must stand behind the submission, optimistic schedules, unresolved financing gaps and contradictory departmental estimates become harder to ignore.

The same discipline should apply to the asset pipeline proposed in Chapter 15. Technical units may originate the condition data, while planning and finance staff test intervention timing and funding assumptions before the submission is consolidated. Before the information reaches central government, however, the responsible agency head should formally sign off on it. This creates a clear institutional owner for the portfolio figures and reduces the risk of central decisions being based on estimates that senior management inside the sponsoring agency has never reconciled.

Nepal Shows What Happens When Approval Becomes Easier Than Completion

Nepal provides a different warning.

A 2026 World Bank assessment found that large infrastructure investments were routinely approved despite persistent implementation problems. At federal level, only about 62 percent of capital-budget allocations were executed on average over the period discussed, while the World Bank estimated that completing 17 National Pride Projects at then-current funding levels would take 41 years.

The figures point to a deeper weakness in portfolio discipline. When new investments continue to enter the budget while existing commitments remain underfunded, annual appropriations cease to represent a credible delivery program and begin to exceed the government's realistic capacity to finance and complete what it has already approved.

The longer-term fiscal consequences of allowing underfunded infrastructure obligations to accumulate were examined in Chapter 13.

The World Bank's recommendation for Nepal is unusually direct: tighten the project pipeline, allow only investment-ready projects into the budget, and delay new approvals until existing commitments are funded.

For finance ministries, the practical implication is clear: inclusion in the annual budget should not substitute for investment readiness. Where land remains unavailable, design is incomplete, counterpart funding is unsecured or procurement preparation is weak, allocating a budget line may simply carry the implementation problem into the next fiscal year.

Do Not Let “Strategic Importance” Become an Escape Route

Every country has projects described as strategic.

Some genuinely are.

That label can also become a way to bypass normal scrutiny.

A project may be politically urgent, nationally symbolic or linked to a major bilateral commitment. Those circumstances can justify faster decisions.

They do not eliminate engineering, fiscal or operating risk.

Where government chooses to proceed despite weak readiness or an adverse independent assessment, that exception should be recorded in the approval paper. The record should identify the approving authority, the specific risks being accepted and any corrective action required before the next irreversible commitment. Politically important projects may sometimes justify an exceptional decision, but allowing the exception to remain informal leaves later officials unable to distinguish a deliberate policy choice from a failure of project control.

The Government Needs an Escalation Map Before It Needs Another Committee

For major projects, I would require a one-page Project Decision Authority Map before procurement begins.

It should identify the decisions that can be taken by the project director, those reserved for the SRO, those requiring the line minister, and those that must return to Finance or Cabinet.

The authority map should be accompanied by measurable escalation triggers. These may include cost movement beyond an approved tolerance, schedule slippage affecting service commencement, unresolved land or permitting deadlines, material changes in demand or safety risk, financing shortfalls, or scope changes large enough to alter the original business case. Government rules should set the applicable thresholds by project type and value so that officials know in advance when an issue must move to a higher decision level. This also improves reporting behaviour inside the project team: escalation becomes a defined management procedure rather than an admission that the project manager has failed.

Independent Review Must Be Allowed to Produce an Uncomfortable Answer

Independent assurance has value only when reviewers are free to reach conclusions that the sponsoring ministry may not welcome. A credible review may find that the business case has weakened, procurement is premature, the project team lacks sufficient capacity, the cost estimate requires substantial revision, or the future operating agency is not ready to take over the asset. None of these findings automatically requires cancellation. They give the approving authority a chance to correct the weakness before additional public money is committed.

Australia explicitly treats Gateway assurance as independent advice while leaving final responsibility with the sponsoring entity and its SRO. The UK's NISTA model similarly leaves departments accountable while the centre provides independent scrutiny and targeted intervention.

The institutional boundary is critical. Independent reviewers need enough authority to challenge assumptions, demand additional evidence and recommend delay, while operational responsibility must remain with the sponsoring ministry. Once the assurance body begins directing day-to-day delivery, responsibility for eventual cost, schedule and performance failures becomes difficult to trace.

What I Would Require Before the Next Major Approval

For a high-value infrastructure decision, the first pages of the submission should make the decision structure visible. They should identify the accountable owner, state exactly what approval is being requested, explain any material assumptions that have changed since the previous decision, summarise the independent challenge undertaken and disclose unresolved professional disagreement. The paper should also specify the event or threshold that would require the matter to return for approval and identify who, on behalf of government, is accepting the residual risk if the project proceeds. A minister should not have to search through forty pages of technical material to discover who owns the decision or what risk is being accepted.

Government Should Make It Easier to Stop Early

Public institutions usually find it easier to approve a new project than to pause one that has already gained political and administrative momentum. This creates a dangerous incentive to keep moving even after the underlying case has weakened. An early pause can preserve public money and leave room for redesign, while the cost of changing direction rises sharply once land has been acquired, consultants mobilised, contracts awarded and public commitments announced.

Project leadership should be judged partly by whether serious problems are raised early enough for government to act. In some cases that will mean delaying procurement, withholding the next funding approval or returning the project for redesign. Such decisions may be uncomfortable, particularly after political expectations have formed, but they are far less damaging than discovering several years later that officials had recognised the problem and lacked a clear route to escalate it. 

Chapter 15 dealt with making future infrastructure obligations visible; this chapter adds the institutional requirement that matters just as much: responsibility for acting on that information must be assigned before the project reaches a point where changing course is prohibitively expensive.


Sources and Further Reading

UK National Infrastructure and Service Transformation Authority. NISTA Major Projects Annual Report 2025–26 (2026).

Australian Government Department of Finance. Gateway Reviews Process (2026).

Australian Government Department of Finance. Lessons Learned — Gateway Reviews (2026).

Australian Government Department of Finance. Guidance on the Assurance Reviews Process, RMG 106 (2026).

Korea Development Institute, PIMAC. Government-Financed Projects — Preliminary Feasibility Study and Total Project Cost Management.

New Zealand Treasury. Quarterly Investment Reporting (2026).

World Bank. Why Nepal Struggles to Build Infrastructure — and What Can Be Done About It? (2026).

The country practices and institutional arrangements above provide evidence from current government investment-management systems. The Project Decision Authority Map, Escalation Triggers, and the recommended structure for recording unresolved professional disagreement are presented here as practical governance measures for application to major public infrastructure programs.


Global Insight 365
Infrastructure, Development Finance and Policy Decisions from the Field

Comments

Popular posts from this blog

Nigeria Beyond Abuja

The Hidden Water Systems That Keep Cities Alive

How Artificial Intelligence Is Transforming Global Infrastructure