When the Backlog Becomes a Fiscal Liability

INFRASTRUCTURE THAT LASTS · PART 4 | CHAPTER 13
Published: 14 August 2026

How Governments Measure Deferred Maintenance Before It Becomes Reconstruction

A maintenance backlog usually arrives quietly.

There is rarely a single Cabinet decision saying that a road network will be allowed to deteriorate. What happens is less dramatic. A pavement programme loses part of its budget. Several bridge repairs move into the following year. Pumps remain in service because replacement funding is unavailable. Drainage work is reduced after another programme becomes more urgent.

Any one of those decisions may be reasonable at the time.

The problem begins when they accumulate.

A road scheduled for relatively inexpensive treatment does not remain in the same condition while it waits for the next budget. Traffic continues. Water enters damaged pavement. Drainage problems remain. Steel continues to corrode. Mechanical equipment continues accumulating operating hours, and another wet season may pass before engineers return.

By the time the item reappears in the following year's programme, the original cost estimate may describe an intervention that is no longer technically appropriate.

That change is often poorly represented in public budgets.

In discussions I have had around infrastructure and development projects, officials generally understand the cost of a new project quickly. There is a contract price, financing package, procurement schedule and completion target.

Deferred maintenance is harder to see because it is distributed across many assets, locations and sometimes several departments.

For that reason, I would not look only at how much maintenance remained unfunded.

I would also want to know what happened to those assets while the funding was unavailable.

The allocation problem behind many of these deferrals was examined in When Maintenance Money Is Not Enough .

The Backlog Is Not Simply Last Year's Unpaid Bill

Assume that an infrastructure agency identifies US$100 million of necessary maintenance and receives authority to spend US$65 million.

It may be tempting to describe the remaining US$35 million as next year's maintenance backlog.

That figure can be useful as a starting point, but simply carrying it forward can become misleading.

Some of the deferred work may still require roughly the same intervention and cost.

Elsewhere, deterioration may have advanced far enough to require more expensive treatment. Some items may have changed category entirely.

A road that required preventive maintenance two years earlier may now need structural pavement rehabilitation.

A bridge component that could once have been repaired may be approaching replacement.

Equipment that required servicing may already have failed.

A credible backlog therefore should not be copied automatically from one annual spreadsheet into the next.

The asset needs to be reassessed.

World Bank guidance on inadequate maintenance has long emphasized the financial consequences of allowing infrastructure to deteriorate until major rehabilitation becomes necessary. The exact cost relationship varies substantially by asset type, traffic, climate, condition and maintenance history.

For that reason, I would avoid telling a finance ministry that every dollar of delayed maintenance produces some universal multiple of future cost.

A stronger case can be built from actual evidence.

The responsible agency can show:

  • what treatment was originally recommended;
  • what it was expected to cost at that time;
  • when and why it was deferred;
  • what the asset's condition is now;
  • what treatment is now required; and
  • how the estimated expenditure has changed.

Applied consistently across a network, this turns the backlog into more than a total of unfunded work.

It begins showing government the financial effect of waiting.

The financing obligation behind long-term asset ownership was discussed in Who Pays After the Ribbon Cutting? .

Maintenance and Rehabilitation Should Not Remain Mixed Indefinitely

An awkward problem appears when an asset remains classified inside the maintenance backlog even though ordinary maintenance is no longer the technically appropriate intervention.

This is partly an engineering issue and partly a public-finance issue.

Routine maintenance may be funded from one budget line. Rehabilitation may require capital approval. External development finance may sometimes be available for larger rehabilitation while ordinary maintenance remains dependent on domestic revenue. Emergency expenditure can follow yet another process.

The asset continues deteriorating regardless of how the government classifies the expenditure.

Over several years, an agency can therefore accumulate a “maintenance backlog” containing very different technical problems.

Some assets still need routine or periodic maintenance.

Others have deteriorated far enough to require rehabilitation.

A smaller group may already be approaching replacement.

Those categories need to be separated.

If inspection shows that a pavement can no longer be economically preserved through the original treatment, continuing to carry the old maintenance estimate understates the government's current exposure.

The same issue is particularly important in bridge management. See Bridge Life-Cycle Asset Management .

World Bank work on railway asset management in Serbia provides a useful example from another sector.

The Bank's life-cycle-cost study reported that existing Serbian railway infrastructure had fallen into serious disrepair following decades of inadequate maintenance. Scarce maintenance resources were often used reactively for immediate emergency needs rather than strategically across the asset portfolio.

The result is important for governments beyond Serbia.

When routine and preventive maintenance remain constrained for long periods, the eventual policy discussion can shift from comparatively modest recurrent intervention toward much larger renewal or reconstruction requirements.

Governments may believe they are limiting maintenance expenditure when part of that expenditure is actually being transferred into a future rehabilitation programme.

The budget classification changes.

The physical requirement remains.

The Backlog Number Should Move With the Asset

Annual budgeting makes infrastructure management difficult because fiscal years have clean start and end dates.

Physical deterioration does not.

A bridge deferred in December remains the same bridge in January, carrying the condition it had when the previous budget year ended.

A pump does not recover because the accounting period has closed.

Pavement deterioration continues between appropriations.

I would therefore treat the maintenance backlog as part of the permanent asset-management record rather than an appendix recreated for each annual budget.

The history matters.

When was intervention first recommended? What was the condition at that time? What was the estimated cost? Why was it postponed? What did the next inspection show? Has the recommended treatment changed?

This does not need to become another large bureaucratic reporting system.

Complex databases can consume resources without materially improving a single budget decision.

The information has value when it changes management action.

Staff movement makes this institutional record particularly important.

In government and project discussions over the years, I have repeatedly seen how easily project knowledge becomes attached to individuals. An engineer remembers why an intervention was postponed. A consultant holds the earlier condition survey. A project team remembers what was agreed.

Then people move.

Two years later, another team sees an asset in poor condition without knowing that the same problem had already been identified and deliberately deferred.

A functioning backlog register should preserve that history.

It should also explain movement in the total value.

Suppose the estimated backlog increases from US$80 million to US$110 million.

The US$30 million increase may have several causes.

New defects may have been identified. Construction prices may have changed. Certain assets may have deteriorated faster than expected. Better surveys may have identified deficiencies that were previously missing from the asset record.

Those explanations have very different implications for government policy.

Simply reporting that the backlog increased by US$30 million tells a finance ministry relatively little.

OECD work on infrastructure asset management connects reliable asset information with institutional responsibility and long-term financial management.

This relationship matters because better asset information should ultimately influence spending decisions rather than merely improve the database.

OECD comparative work also shows that even among relatively advanced public administrations, whole-of-life asset-management practices remain uneven.

For developing countries expanding their infrastructure stock rapidly, weak life-cycle management can become more consequential because the portfolio itself is growing at the same time.

A Growing Backlog May Signal More Than a Funding Shortage

The first reaction to a rising backlog is usually to ask for a larger maintenance budget.

Sometimes that is the correct response.

In other cases, the backlog is also revealing an institutional problem.

An agency may have difficulty spending the maintenance funding already approved because procurement is slow.

Unit costs may be outdated.

Inspection information may be incomplete.

There may be too few qualified engineers to prepare, procure and supervise the required work.

Responsibilities between national and provincial agencies may be unclear.

Or the infrastructure network may simply be getting older faster than the current maintenance system was designed to manage.

Each of these situations can produce a growing backlog.

The required response is different.

I would therefore be uncomfortable if a persistent backlog were presented to Cabinet only as evidence that the maintenance allocation was too small.

Additional money will not by itself repair a procurement system that cannot convert approved budgets into executed work.

Nor will it solve an asset-management system that cannot identify the condition of the infrastructure it owns.

ADB's work on road-maintenance financing considers funding within this wider institutional setting. Its analysis connects sustainable financing with road-asset management, public financial management, cost recovery and the mechanisms through which maintenance revenue is collected and spent.

That is closer to the problem governments actually face.

There is also a longer-term issue for countries that continue building rapidly.

Every new road, bridge, water facility or power installation creates another future maintenance requirement.

This is not an argument for stopping necessary infrastructure development.

Countries facing serious infrastructure shortages cannot wait until every existing asset is in perfect condition before building anything new.

But before another major investment programme is approved, I would want senior officials to see the direction of the existing maintenance backlog.

A backlog that is measured, prioritised and managed is one thing.

A backlog increasing faster than the responsible institution can inspect, cost or finance it is a different fiscal and management problem.

The broader financing problem is discussed in When Governments Know What Must Be Done—but Cannot Yet Fund It .

What I Would Put Before Senior Government

I would not place the complete maintenance database in front of a minister or Cabinet committee.

The supporting database and engineering evidence need to exist.

The executive submission should be shorter and designed for decision-making.

I would use a Deferred Maintenance Review.

Executive Item What Government Should See
Current backlog Present estimated value of verified deferred work and how it has changed since the previous review.
Maintenance still viable Deferred assets where the originally intended maintenance treatment remains technically appropriate.
Shifted to rehabilitation Assets whose condition has deteriorated enough to require a larger intervention or different budget treatment.
Urgent safety exposure Assets requiring immediate technical restrictions, protection, investigation or emergency intervention.
Reason for backlog growth Distinguish deterioration, price changes, newly identified defects, procurement delay and additional network coverage.
Decision required Identify the cases where another year of delay may materially affect cost, safety, service continuity or the choice between maintenance and rehabilitation.

If the total backlog has increased, senior government should be able to see why.

A small number of assets may account for a large part of the increase and require immediate attention.

Another group may have remained deferred without material deterioration and may continue to wait within a managed programme.

They should not automatically receive the same level of concern simply because they sit in the same backlog total.

Not every maintenance item belongs at Cabinet level.

The cases that matter are those where delay is changing cost, safety, service reliability or the technically appropriate form of intervention.

The purpose of the review is to alter decisions where necessary.

If the backlog review never changes a work programme, intervention date, procurement action or funding decision, its practical value is limited.

Bring the Existing Portfolio Into the Next Capital-Investment Decision

I would use backlog information in one additional place: the discussion of new infrastructure investment.

When government considers another major road, bridge, power facility or treatment plant, the proposal naturally explains why the new infrastructure is needed.

Economic benefits are calculated.

Construction costs are estimated.

Financing arrangements receive detailed attention.

I would add a short view of the infrastructure portfolio the responsible institution already owns.

Before approving a large expansion programme, senior decision-makers should know whether that institution's maintenance backlog is declining, stable or increasing.

This information would not automatically decide whether the new project proceeds.

There are circumstances where new investment remains necessary despite substantial existing maintenance pressure.

A missing transport corridor may be constraining trade. A city may urgently require additional water supply. Electricity shortages may make new generation or transmission unavoidable.

The correct decision may still be to build.

But that decision should be made with an understanding of the asset portfolio the institution is already struggling to operate and preserve.

This distinction has become increasingly important to me through years of involvement around public infrastructure and development discussions.

A country can become quite capable at preparing, financing and constructing new projects while institutional capacity for long-term ownership develops more slowly.

The weakness may not be visible during construction.

Several years later, it becomes visible through deteriorating roads, equipment failures, emergency interventions and a maintenance programme whose cost continues increasing despite repeated budget discussions.

At that stage, the useful question is no longer simply how much maintenance was postponed during the previous year.

Government needs to understand how condition deterioration is changing the future cost of preserving the assets it already owns.

That information belongs in the investment discussion before the infrastructure portfolio expands again.

Editorial Note

This article uses the term fiscal exposure to describe potential future public expenditure associated with deterioration of existing infrastructure.

Deferred maintenance is not automatically equivalent to recognised public debt, a provision or an accounting liability.

Formal valuation and classification should follow the applicable public-sector accounting framework, engineering assessment, asset-management policy, budget rules and the legal responsibilities of the asset owner.

Sources and Further Reading

OECD — Management of Assets Throughout Their Life Cycle
Management of Assets Throughout Their Life Cycle: Evidence from the Infrastructure Governance Indicators
OECD Working Papers on Public Governance No. 89, 2026. Examines infrastructure condition, asset information, institutional responsibility, professional capability and financial practices across the life cycle.

OECD — Government at a Glance 2025
Management of Asset Performance Throughout the Life Cycle
Provides comparative evidence on government asset-management policies, monitoring, accountability and whole-of-life financial management.

World Bank — Inadequate Maintenance
Inadequate Maintenance
Explains how under-maintenance can increase infrastructure life-cycle costs and move assets toward more expensive rehabilitation.

World Bank — Serbia Railways Asset Management Plan Using Life-Cycle Costs
Serbia Railways Asset Management Plan Using Life-Cycle Costs
Shows how life-cycle costing can support rail asset management and documents the consequences of long-term inadequate and reactive maintenance.

World Bank — Resilient Transport in the Middle East and North Africa
Investing in Resilient Transport to Drive Inclusive Growth
Includes Lebanon, where financial constraints and accumulated maintenance needs contributed to deteriorating road conditions and costly repairs.

Asian Development Bank — Road Maintenance Financing and Cost Recovery Options
Road Maintenance Financing and Cost Recovery Options
Examines road-maintenance financing together with asset management, public financial management and institutional arrangements across developing Asia and the Pacific.


Related Articles

→ When Maintenance Money Is Not Enough

→ Who Pays After the Ribbon Cutting?

→ Bridge Life-Cycle Asset Management

→ When Governments Know What Must Be Done—but Cannot Yet Fund It


Peter Kwon
GLOBAL INSIGHT 365
Independent perspectives on infrastructure, development and a changing world.

© 2026 Peter Kwon. All Rights Reserved.