When an Infrastructure Project Starts to Go Wrong.
Published: 9 August 2026
How Governments Can Detect Problems Early, Stabilize Troubled Projects, and Recover Cost, Schedule, and Public Trust
A troubled infrastructure project rarely announces itself with one dramatic failure.
More often, the warning signs appear quietly.
A drawing is issued three weeks late. A payment certificate waits on somebody's desk. Land that was supposed to be available is still occupied. The contractor reduces equipment at the site. The consultant requests another clarification. A variation that looked small in April remains unresolved in August.
The monthly report may still say that the project is 63 percent complete.
That number can be reassuring while important parts of the project are already moving in the wrong direction.
World Bank contract-management tools reflect this reality. The STEP Contract Management Module tracks milestones, key performance indicators, deliverables and payments, while also allowing contract events such as variations, claims and disputes to be recorded during implementation.
A single completion percentage therefore cannot tell senior officials everything they need to know about project health.
I have had many discussions over the years with government officials in Korea, Cambodia, Malaysia, Nigeria, Ghana and Timor-Leste on construction, energy, natural resources and rural modernization.
One pattern has remained remarkably consistent.
When a project begins to struggle, the contractor, supervision consultant and responsible ministry may each describe the cause differently. Sometimes each of them is partly right.
That is exactly what makes some projects difficult to recover.
Many warning signs begin earlier, during procurement and the first stages of implementation. For that stage, see After the Financing Is Approved .
Start With the Dependency, Not the Completion Percentage
If I walked into a ministry on Monday morning and inherited a project that was already slipping, I would not begin by asking:
What is the current completion percentage?
I would ask another question:
Who is waiting for whom?
The contractor may be waiting for drawings. The engineer may be waiting for a government decision. The ministry may be waiting for payment authority. The site team may be waiting for land access, customs clearance or utility relocation.
In another project, all external constraints may already have been removed while the contractor lacks sufficient working capital, equipment, materials or qualified personnel to maintain the programme.
These are very different problems.
They should not all be grouped under the convenient heading of “project delay.”
Delay is the visible result. The management task is to identify the dependency or failure that is producing it.
This distinction matters because demanding acceleration from the contractor achieves little when a government obligation is still preventing the critical activity from starting.
The reverse is also true. Once government-side constraints have genuinely been removed, continued weak mobilisation begins to provide clearer evidence about contractor performance.
Compare the Project File With the Construction Site
There comes a point in a troubled project when formal reports need to be tested against physical observation.
I have been in government discussions where the written explanation of a project sounded manageable. Once the conversation moved away from prepared papers and into practical questions about land, approvals, payments, manpower and timing, the picture changed.
This is why senior project leadership should occasionally leave the meeting room.
World Bank's 2024 Contract Management: Practice guidance is direct on this point. It states that the employer needs a good understanding of what is happening on an infrastructure site and recommends involvement of the employer's technical experts in joint site visits with the contract manager.
A minister does not need to inspect reinforcing steel personally.
Government decision-makers do, however, need reliable technical people who can establish whether the project described at headquarters resembles the one that actually exists on site.
I would look for ordinary evidence:
- How many major pieces of equipment are operating today?
- Has the workforce increased, remained stable or declined?
- Are critical materials arriving when the programme requires them?
- Which structure or work front has shown little movement for several weeks?
- Which approvals are still blocking construction?
- What does the contractor plan to complete during the next 30 days?
The last question is especially useful.
A conventional progress report largely describes what has already happened. A recovery decision has to establish what must happen next.
Before Blaming the Contractor, Examine the Government Side
There are poorly performing contractors.
Some bid too aggressively, underestimate working-capital requirements, mobilise insufficient resources or assign project teams that are not strong enough for the work.
Governments need to deal firmly with genuine contractor underperformance.
But contractor failure is not the only cause of project delay.
Site possession, resettlement, utility relocation, incomplete design information, permits, slow approvals and overdue payments can disrupt a construction programme just as seriously.
The recovery review should therefore identify both contractor-side and employer-side constraints.
For each major issue, I would want four facts recorded:
- What contractual or administrative action remains outstanding?
- Who is responsible for it?
- How long has it remained unresolved?
- Which activities, payments or completion dates are affected?
Several years ago, I might have looked at a troubled construction project more quickly as a contractor-performance problem.
After many discussions around infrastructure and development projects, I would examine the entire execution chain today.
Sometimes the most useful recovery meeting is the one where overdue government actions are placed on the same table as the contractor's failures.
Many of these problems can be reduced during preparation. See From Project Concept to Funding Proposal .
Control Variations Before They Accumulate
A variation is not automatically evidence that a project is failing.
Ground conditions can differ from surveys. Designs may require adjustment. Quantities change. Governments sometimes have legitimate reasons to modify requirements.
The risk grows when variations accumulate faster than decisions are being made.
A contractor prices a change. The consultant challenges part of the valuation. The employer requests additional evidence. Another instruction is issued while the first remains undecided. The time consequences are left for later.
After several months, the project can reach a point where neither the likely final contract value nor the realistic completion date is clear.
At that stage, executives need more than a count of how many variations have been issued.
I would ask:
How many variations remain undecided, what financial exposure do they create, and which ones affect the critical path?
Variation management should connect technical necessity, valuation, time consequences, approval authority and contractual documentation.
A variation register should therefore be an active decision tool, not a storage place for unresolved correspondence.
When Normal Project Management Is No Longer Enough
At some point, an ordinary monthly progress meeting may no longer be adequate.
Once delay, claims, employer obligations, contractor performance, payments and variations begin interacting, I would establish a temporary Project Recovery Team.
The team should remain small, but it needs actual authority.
Membership should be based on the ability to resolve problems rather than on institutional protocol.
Depending on the project, that can mean:
- the project director or senior implementing-agency official;
- technical and engineering authority;
- the supervision consultant or contract manager;
- contract and procurement expertise;
- finance and payment authority;
- officials able to resolve land, utility or permit issues; and
- legal advice where claims or contractual remedies have become significant.
The purpose is not to spend weeks reconstructing blame for everything that happened during the previous two years.
The original contractual baseline still matters.
For recovery management, however, the government also needs a current factual baseline: actual physical progress, cash and payment status, unresolved employer obligations, live claims, pending variations, current resources, remaining critical-path activities and a realistic completion forecast.
Only after that information is assembled can the responsible authority decide whether recovery under the existing contract remains realistic.
A Practical 90-Day Project Recovery Framework
The following framework is not a World Bank or ADB prescribed procedure.
It is a practical management framework for a government facing a project that has already entered serious difficulty. It draws on the contract-management principles emphasized by the World Bank and ADB: current information, clear responsibility, milestone tracking, timely decisions, contract discipline and documented corrective action.
| Recovery Window | What Government Should Do | Required Output |
| First 10 Days | Establish the facts. Verify physical progress, outstanding payments, land and utility access, approved and pending variations, live claims, workforce, equipment and the current critical path. | One agreed factual project-status sheet |
| Days 11–30 | Assign every blocking issue to somebody with authority. Clear urgent government obligations. Require a credible revised programme linked to resources, payments and site conditions. | Recovery actions with named owners and dates |
| Days 31–60 | Compare promised recovery with actual site performance. Resolve or escalate major variations and claims. Bring the financing institution into matters requiring its review, approval or project restructuring. | Evidence that recovery is occurring—or evidence that it is not |
| Days 61–90 | Decide whether the existing arrangement remains viable. Continue recovery, formally restructure within contractual rules, strengthen management or prepare the remedies permitted under the contract. | A defensible government decision based on verified performance |
The first thirty days are particularly revealing.
If government removes its own bottlenecks, the contractor mobilises additional resources, critical activities begin moving and communication improves, recovery under the existing arrangement may still be realistic.
If the constraints are removed and little changes on site, the contractor-performance question becomes much clearer.
What I Would Put on the Minister's Desk
I would not use a 70-page progress report as the primary document for a senior recovery decision.
The full technical and contractual record must remain available, but the decision document itself can be much shorter.
At the top I would show:
Original completion date / Current realistic completion forecast / Original contract value / Current forecast contract value
Below that, I would use a small action table.
| Issue | Responsible Party | Decision / Action Needed | Deadline | Consequence of No Action |
| Land access | Government | Release remaining work section | 14 days | Critical works cannot start |
| Contractor cash flow | Contractor / Employer | Verify certified payments and contractor financing | 7 days | Mobilisation continues to decline |
| Design change | Engineer / Employer | Approve, revise or reject | 10 days | Variation and EOT exposure increases |
| Critical-path activity | Contractor | Resource-backed recovery programme | Immediate | Completion forecast slips further |
| MDB approval issue | PIU / Ministry / Financier | Submit complete request | Defined date | Procurement or variation remains blocked |
At the bottom I would leave one line:
Decision required from the Minister this week: ____________________.
That is the level at which a senior management document becomes useful.
The engineering, contractual, financial and legal evidence remains behind it for review when required.
Do Not Move to Termination Before the Contractual Position Is Clear
When a project has become politically embarrassing, termination can sound decisive.
Sometimes termination is necessary.
It is nevertheless one of the most consequential decisions an employer can make on a major infrastructure contract.
An unfinished project may involve performance security, unpaid certificates, claims, subcontractors, imported equipment, incomplete structures, temporary works, insurance, design liability and a construction site that another contractor may eventually have to inherit.
A replacement procurement can also require substantial time.
Before exercising remedies such as delay damages, withholding payment, calling security or termination, government should understand both the contractor's performance record and its own compliance with the contract.
Were notices issued correctly?
Were certified payments made when required?
Was possession of the site provided?
Are instructions and variations properly documented?
Can the employer demonstrate the contractual basis for the proposed remedy?
The answers matter if the project later enters formal dispute proceedings.
Where disagreement can still be resolved within the contract, early resolution is usually preferable to allowing positions to harden unnecessarily.
FIDIC's recent discussion of contract management and dispute avoidance similarly emphasizes effective contract administration and resolving disagreements as they arise.
Tell the Development Partner Before the Problem Becomes a Crisis
This is particularly important for World Bank, ADB and other development-financed projects.
A government may be tempted to solve a serious implementation problem internally before discussing it with the financier.
Sometimes that is possible.
In other circumstances, waiting creates a second problem.
If a major variation will require review, procurement has to be changed, disbursement is substantially behind plan or project restructuring may become necessary, the financing institution needs time to understand the situation.
I would not arrive with a crisis and a request for approval on the same day.
I would bring a structured record:
- what happened;
- what the contract and financing documents require;
- which obligations have been fulfilled;
- which remain outstanding;
- what corrective action has already been attempted;
- how much time and money are exposed; and
- what solution the government currently recommends.
A development partner cannot manage the government's project on its behalf.
But a government that understands and documents its own problem is in a much stronger position to request the right support.
For the government side of that discussion, see At the Table With Development Partners .
Recovery Has to Be Demonstrated by Site Performance
Political leaders naturally want a new completion date.
I would be cautious about providing one before the recovery programme has been tested.
A date produced before resources, payments, site access and critical-path activities begin responding is still an assumption.
Watch what actually changes.
Does the contractor mobilise the promised equipment and personnel? Are certified payments being processed? Are outstanding decisions being made? Are major variations closing? Has access to critical work fronts improved? Is the critical path beginning to move?
Thirty or forty-five days of actual performance can provide more useful evidence than another optimistic completion date announced immediately.
Political urgency is real and engineers cannot simply disregard it.
Engineering and contractual realities are equally real.
Competent project management is the process of bringing those constraints into the same decision.
Closing
A troubled project does not need a more optimistic version of the same progress report.
It needs an accurate diagnosis of the obstacles that are still controlling the outcome.
Someone with authority has to decide what government must fix, what the contractor must correct, what the engineer needs to determine and which unresolved matters can no longer be carried forward into another reporting period.
Every recovery action should have a responsible party, a deadline and evidence by which completion can be verified.
After that, the site should determine whether the recovery strategy is working.
If physical and administrative movement returns, continue the recovery.
If the agreed constraints are removed and performance still does not improve, government should make the harder contractual decision while a viable project can still be protected.
Once construction is finally completed, another responsibility begins: protecting the asset that has been built. See Bridge Life-Cycle Asset Management .
Editorial Note
The 90-Day Project Recovery Framework in this article is an editorial and practical management framework developed for GLOBAL INSIGHT 365. It is not an official World Bank, ADB or FIDIC procedure.
Its application should be adapted to the governing construction contract, national law, financing agreement, procurement requirements and the specific authority of the employer, engineer, contractor and financing institution.
Sources and Further Reading
World Bank — STEP Contract Management Module
STEP Contract Management Module
Tracks contract milestones, KPIs, deliverables, payments and other implementation events throughout the contract cycle.
World Bank — Contract Management: Practice
Contract Management: Practice — Procurement Guidance, June 2024
Practical guidance covering variations, site visits, progress monitoring, employer responsibilities and contract administration.
World Bank — Project Procurement Framework
Project Procurement Framework
Provides the wider procurement and contract-management framework for World Bank Investment Project Financing.
Asian Development Bank — Contract Management
Contract Management — Business Guide
Covers preparation and planning, contract administration during implementation, performance management and contract closure.
Asian Development Bank — Project Administration Instructions
Project Administration Instructions
Current ADB procedures for project administration, changes, project performance monitoring and portfolio management.
FIDIC — Contract Management and Dispute Avoidance
The Intersection Between Contract Management and Dispute Avoidance
Discusses contract administration, project-specific risk management and resolving disagreements before they escalate.
Related Articles
→ After the Financing Is Approved
→ From Project Concept to Funding Proposal
→ At the Table With Development Partners
→ Bridge Life-Cycle Asset Management
Peter Kwon
GLOBAL INSIGHT 365
Independent perspectives on infrastructure, development and a changing world.
© 2026 Peter Kwon. All Rights Reserved.
Comments
Post a Comment
Welcome to Global Insight 365.
We value thoughtful discussions and diverse perspectives.
Please share your ideas with respect and kindness.
Together, we build a trusted global knowledge
community.
Global Insight 365에 오신 것을 환영합니다.
우리는 깊이 있는 토론과 다양한 관점을 소중히 생각합니다.
서로를 존중하는 마음으로 여러분의 생각을 나누어 주세요.
함께 신뢰받는 글로벌 지식 공동체를 만들어 갑시다.